Assembly

For the installation of the aquatherm-climasystem follow the manufacturer´s recommendations – for plaster works follow the regulations of the plaster manufacurer. Suspended cassette-ceilings and prefabricated
construction elements have to be installed according to dry construction guidelines resp. manufacturer´s advices.
Raw ceilings and walls must have a firm base for the installation of the heating grids. The aquatherm-climatherm comes in variable lengths offered, so that cutting at the building site ordinarily is not necessary.
The grids must be connected by means of heating element fusion.
At first the aquatherm-climasystem is fixed with the attached wall brackets (2 pieces per grid) at the raw wall or ceiling. Further fixing occurs through the pre-mounted fixing rail.
A sufficient number of fixings is to be intended!
The fixing element with plug (see picture in the middle below) in conjunc-tion the with fixing rail and the grids can be used as plaster base. 

|